The City of Dexter reports that Encore and the Senior Center have reached an agreement that the boards of both organizations have approved. In essence, the agreement assures that everything will remain the same for the Senior Center through December 31, 2020. Starting January 1, 2021, the Senior Center will only have access to the building from 8:00 a.m. to 4:00 p.m. and will not be able to rent out their space since Encore will be using the space for evening events.

Advertisement

The agreement between the two parties lasts until December 31, 2023.

Central Street completion

The sidewalk cuts are almost finished curing and completion is expected sometime this week, weather permitting. The City will announce an opening date as soon as it has been determined.

Mill Creek Park Phase II

The City reports that the initial, tentative timeline for the project that will extend the shared pathway from Mill Creek Park to the schools is as follows:

  • January: Bid for the project are processed
  • February-June: Site prep, clearing, excavation, pier installation, boardwalk construction
  • July: paving, gravel shoulders, seeding, mulching